US 41 AC Water Main Replacement Project – UPDATE via PDF available HERE
January 15
Work Completed Weeks: January 1, 2018 through January 8, 2018
o Completed the installation of the water main at US 41 at Floyd St. west side.
o Directional drilled the water main at US 41 and Hillview St.
o Began to install the water main on Hillview St.
o Restored the asphalt after the water main installation on Hillview St.
o Chlorinated/dechlorinated the water mains on Arlington St., Datura St. and Wisteria St.
o Restored the concrete and asphalt on Floyd St.
Work Scheduled Week of: January 15, 2018
o Complete the installation of the water main on Hillview St.
o Restore the asphalt on Hillview St.
o Set up MOT for lane shifts on Bahia Vista and road closure on East Ave.
o Begin the extension of the water main from East Ave. to Bahia Vista St.
Work Scheduled Week of: January 22, 2018
o Continue installation of the new water main on Bahia Vista.
o Jack and bore across Bahia Vista at East Ave.
o Directional drill on Bahia Vista from East Ave. to School Ave.