Good Afternoon,

 Work Completed this Week:

To date, the phase 3 contractor has installed 220 LF of gravity sewer pipe on Osprey Ave.  Over the past two weeks the contractor has been focused on rebuilding Osprey Ave in the work zone where the pipe was installed. Curbs on Osprey Ave have been poured and road base placed and compacted. Work on the Lincoln & Osprey intersections have finally begun.  The contractor tied-in the new stormwater drainage pipe to the existing stormwater structure and ran the pipe across Osprey Ave.

 

The forecast for the following week shows wet weather.  Pending severe weather, the following work is scheduled:

 

Work Upcoming in Next Week:

  • Continue restoration work on Osprey Ave. South of Lincoln Drive.  This includes installing new curbs, gravel road base, and the first 2” lift of asphalt.
  • Install Wellpoints on Osprey Ave south to Alta Vista Street.
  • Continue gravity sewer installation and set first manhole
  • Osprey Ave. and Lincoln Drive intersection improvements.  The contractor will continue the stormwater drainage pipe and stormwater inlets on Osprey Ave and Lincoln Drive.

Thanks,

Tony

Anthony Centurione, PE

Utilities Engineering Manager

City of Sarasota

Lift Station 87 Field Office

824 S. Osprey Ave

Sarasota, FL  34236

941.316.8490 (office)

941.316.8491 (fax)

anthony.centurione@sarasotaFL.gov

 

Categories: Sarasota

0 Comments

Leave a Reply

Avatar placeholder

Your email address will not be published. Required fields are marked *