US 41 AC Water Main Replacement Project – UPDATE via PDF available HERE
December 18
Work Completed Weeks: December 4, 2017 through December 11, 2017
o Directional drilled the water main under US 41 at Prospect St.
o Completed the installation of the water main on Prospect St. from the east side of US 41 to East Ave.
o Completed the installation of the services to the customers on Hyde Park St. east of US 41.
o Flushed the water main with the pig on Prospect St. from the west side of US 41 to East Ave.
o Directional drilled the water main under US 41 at Clematis St.
o Completed the installation of the water main on Clematis St. at US 41 (both sides).
o Pressure tested water mains on Datura St., Clematis St. and Wisteria St.
Work Scheduled Week of: December 18, 2017
o Directional drill the water main under US 41 at Floyd St.
o Install the water main at US 41 at Floyd St. west side.
o Chlorinate the water mains on East Ave. from Bahia Vista St. to Arlington St., Waldemere St. and Arlington St.
o Possibly pressure test Hyde Park St. and Prospect St.
Work Scheduled Week of: December 25, 2017
o Install the water main at US 41 at Floyd St. west side.