US 41 AC Water Main Replacement Project  – UPDATE via PDF available  HERE

January 15

Work Completed Weeks: January 1, 2018 through January 8, 2018

o Completed the installation of the water main at US 41 at Floyd St. west side.

o Directional drilled the water main at US 41 and Hillview St.

o Began to install the water main on Hillview St.

o Restored the asphalt after the water main installation on Hillview St.

o Chlorinated/dechlorinated the water mains on Arlington St., Datura St. and Wisteria St.

o Restored the concrete and asphalt on Floyd St.

Work Scheduled Week of: January 15, 2018

o Complete the installation of the water main on Hillview St.

o Restore the asphalt on Hillview St.

o Set up MOT for lane shifts on Bahia Vista and road closure on East Ave.

o Begin the extension of the water main from East Ave. to Bahia Vista St.

Work Scheduled Week of: January 22, 2018

o Continue installation of the new water main on Bahia Vista.

o Jack and bore across Bahia Vista at East Ave.

o Directional drill on Bahia Vista from East Ave. to School Ave.

Thank you